Operations And Supply Chain Management 14 Edition By Jacobs – Test Bank
Chapter 04
Project Management
True / False Questions
1. |
Project management can be defined as planning, directing, and controlling resources to meet the technical, cost, and time constraints of the project. |
2. |
A project may be defined as a series of related jobs directed toward some major output and requiring a significant period of time to perform. |
3. |
The second step in managing a project is writing the statement of work. |
4. |
An event unit package is a subdivision of a project. |
5. |
Complex projects are often subdivided into a series of tasks that are typically configured to be not longer than several months in duration. |
6. |
A work breakdown structure is used in project management but it is not used when the critical path method is involved. |
7. |
The fact that organizations are flattening is one of the reasons that project management is important. |
8. |
The Gantt chart is an example of a project control chart. |
9. |
Upper-level management must decide between pure, functional, and matrix structures as ways to organize projects. |
10. |
One of the disadvantages of a pure project organizational structure is that the project manager has full authority over the project. |
11. |
One of the advantages of a functional project organizational structure is that a team member can work on several projects. |
12. |
A matrix project attempts to blend properties of functional and pure project structures. |